Tuesday, February 4, 2014

Nuclear Event - Maryland : Reactors at nuclear power plant in southern Maryland shut down last week after an electrical malfunction

Nuclear regulators send inspectors to Calvert Cliffs

Reactors at nuclear power plant in southern Maryland shut down last week after an electrical malfunction

  • Control rod problem shuts down Calvert Cliffs reactor
The Nuclear Regulatory Commission announced Monday that it is conducting a special inspection at the Calvert Cliffs nuclear power plant in Southern Maryland after an electrical malfunction caused the two reactors there to shut down.
The plant, which restarted both reactors over the weekend, suffered the shutdown after snow and ice during a storm Jan. 21 apparently affected a ventilation louver filter and caused a short circuit. After the electrical supply system shut down, so did several plant systems and components that rely on electricity, the nuclear regulatory agency said Monday.
Those components included motors for moving control rods and water circulating pumps for the Unit 2 reactor, the agency said. The main turbine control circuit for the Unit 1 reactor also malfunctioned after the electricity loss.

Both units shut down as a result, with "no impacts on public health and safety," the agency said.
The three-person inspection team began working at the plant Monday, the commission said.
"We want to gain a better understanding of the chain of events that caused both of the reactors to simultaneously shut down and equipment anomalies subsequent to the plant trips," said Bill Dean, the commission's administrator for the region that includes Maryland, in a statement. "This inspection is designed to shed additional light on not only why the outages happened but how the plant operators handled them."
A Constellation Energy Nuclear Group spokesman said in an email that federal reviews after shutdowns are common, adding that the company welcomed the inspection at its plant.
"Operators followed their training and performed well during the shutdowns," said Kory Raftery, the spokesman. "The site's multiple safety systems responded as designed."
But Neil Sheehan, a Nuclear Regulatory Commission spokesman, said such inspections are not common.
Read More Here
Related
.....
Holland Sentinel
    • Inspections find flaws in nuclear plant mechanism during scheduled outage

  • “NRC inspectors have been reviewing the plant’s inspections and assessments and are reviewing the licensee’s replacement and repair plans, which will be completed prior to plant startup,” said Viktoria Mitlyng, senior public affairs officer for the NRC in this region. “The NRC will continue to evaluate and validate the licensee’s response to the issue to ensure plant safety.”
    The plant shut down Jan. 19 to replace 64 fuel assemblies and conduct maintenance, tests and inspections on equipment including the reactor vessel and its two low-pressure turbines.
    The facility remains offline.
    The control rod drive mechanism housings are part of the reactor coolant system boundary designed to prevent reactor coolant from leaking, Mitlyng said. There was no evidence of leakage.
    Read More Here
.....
Enhanced by Zemanta

Nuclear Event - State of Delaware, [Salem Nuclear Power Plant]

Earth Watch Report  -  Nuclear Event





salem 2 at right.jpgThe Salem 2 nuclear reactor, seen at right at PSEG Nuclear's Artificial Island generating complex in Lower Alloways Creek Township, returned to service this morning.
  South Jersey Times By South Jersey Times

Salem Unit 2 nuclear reactor shut down after control rod issue


on January 31, 2014 at 2:21 PM
LOWER ALLOWAYS CREEK TWP.
.....

Nuclear Event USA State of Delaware, [Salem Nuclear Power Plant] Damage level Details

.....
Description
Salem Unit 2 was manually taken offline by control room operators at 10:01 a.m. Friday, according to Joe Delmar, spokesman for PSEG Nuclear, after an issue with one of the control rods. There was no threat to the health and safety of the public, and no issues with the manual shutdown, he added. A return to service is not available at this time. The plant had been online 430 consecutive days, Delmar said, and it produces 1175 megawatts of electricity �" enough power for a million homes. On Friday morning, Delmar said control room operators were conducting monthly testing on the control rods used to control reactor power. During the monthly testing, one of the control rods dropped out of its expected position, he said. At this time, the expected cause of the control rod mispositioning is believed to be a blown fuse with a more detailed investigation under way. In a pressurized water reactor like Salem, the control rods are inserted into the top of the fuel assemblies. There are 193 nuclear fuel assemblies inside the Salem reactor core and 53 control rods. In response to the control rod mispositioning, Delmar said control room operators took appropriate actions including adding boron to the reactor water to reduce power level and maintain shutdown margin as required by NRC technical specifications. Operators then made the subsequent conservative decision to safely shut the unit down, he said. Salem Unit 1 and the neighboring Hope Creek plant were not impacted and remain at full power. Salem 2 is one of three reactors operated by PSEG Nuclear at its generating site on Artificial Island here.

.....



Enhanced by Zemanta